196% Increase
The Department of Transportation took approximately .329 acres and additional easements for completion of roadway improvements related to ramp improvements over I-95 in Lumberton; deposit of $97,850; settlement of $290,000 ($192,150 or 196% increase).
A partial taking of .329 acres of 2.239 acres of commercially zoned land being used for a convenience store gas station and taking for various utility, drainage and construction easements.
Settlement
Robeson County
Department of Transportation v. Sonny Oliver Realty Co., 12-CVS-551
Settlement reached July 10, 2014.
David W. Murray, The Odom Firm, PLLC of Charlotte.